The CNC busbar processing machine is suitable for processing parts that are periodically put into production. The market demand of some products is cyclical and seasonal. If a special production line is used, it will not be worth the loss. The processing efficiency of ordinary equipment is too low, the quality is unstable, and the quantity is difficult to guarantee. After the trial cutting of the first piece of the machining center is completed, the program and related production information can be retained, and the production can be started with a short preparation time for the next product reproduction. Today, let's take a look at the precautions for the operation of the CNC busbar processing machine:
So I would like to remind everyone that when you use the busbar processing machine in the future, you must always do his cleaning work well.
Busbar processing machines are widely used in high and low voltage switch cabinets, substations, bus ducts, bridges, electrical switches, communication equipment, household appliances, shipbuilding, office automation equipment, elevator manufacturing, chassis and cabinet manufacturing and other electrical complete sets of manufacturing industries. The following editor will introduce to you the difference between the models of busbar processing machines.
Before the operation of the CNC busbar processing machine:
1. Before starting the machine for the first time, the fuel tank must be filled with oil to avoid damage to the oil pump. 2. You must read this instruction manual carefully and be familiar with the structure, performance and operation method of the machine. 3. Do not wear a scarf or a coat. 4. Work in the correct way to stop and get out of danger as soon as possible in the event of a breakdown. 5. If the ambient temperature is lower than 0°C, it should be turned on for a few minutes before working.
4. (1) The three processing units of punching, shearing and folding in a single pump station are controlled by one pump station respectively, which can realize the operation and processing of the three processing units in sequence
In operation of CNC busbar processing machine:
1. The installation, debugging (matching the mold, adjusting the blade gap) or dismantling the mold must be carried out by personnel familiar with the machine in accordance with the prescribed procedures. 2. When the machine is working normally, do not put your hand or part of your body between the upper and lower molds (blade) to avoid accidents. 3. All sundries and tools should not be placed on the workbench to avoid accidents caused by rolling into the mold or knife edge. 4. Since the machine can be operated by many people, there must be a special person responsible for directing the production. 5. Be sure to select the gap between the shearing blade and the die and the radius of the bending fillet according to the thickness of the bus bar (or aluminum row). 6. Be sure to stop the machine when changing the mold to avoid danger. 7. During operation, be careful when holding the workpiece and waiting for the slider to go down. 8. The sharpness of the blade and the die edge should be checked regularly. If the edge is found to be dull, it should be reground or replaced in time. 9. Keep the oil clean and the oil circuit unblocked, and add lubricating oil to the moving parts of each unit every shift. 10. The electrical and hydraulic components must ensure flexible movement and correct position. When abnormal phenomena are found, they must be stopped immediately for inspection.
2. Influence of tool error: In processing, because the tool used has automatic exchange function, it also brings tool exchange error while improving productivity. When using the same tool to process a batch of workpieces, due to the frequent and repeated tool change, the tool holder has a repeated positioning error relative to the spindle taper hole, which reduces the machining accuracy.
After the CNC bus processing machine is operated:
After the operation, be sure to shut down safely in the following order: (1) Turn off the working buttons of each unit. (2) Turn off the power switch on the operation panel. (3) Turn off the main circuit air switch. (4) Reasons why the installation of the busbar of the power switch in the shutdown workshop does not meet the requirements: (1) The cable construction units have not coordinated well, and only the cables laid by themselves can pass through.
(2) They did not coordinate well with the civil engineering unit when plugging the high-voltage shaft, and the construction personnel did not master the plugging technology.
(3) The material is not up to standard, and the purchaser does not purchase the cable fixing bracket and the terminal (line lug) according to the standard.
(4) The area left by the construction major for the electrical major to make strong electric shafts is too small, which makes the layout of strong electric shafts difficult.